Construction Schedule

CEE is currently engaged in a Campus Enhancement Plan that has been carefully designed to limit disruption to activities on our campus. Below is a detailed schedule of the construction phasing and the impact it will have on campus.

2017-2018 School Year
September – December 2017: All classrooms will remain where they have been traditionally been, however, there will be some minor changes to campus. Learn more about them here

December 18, 2017 – January 5, 2018: Winter Break

January 2018: The building on LaCienega will be completed and third grade will move into new classrooms in the building while PE will move into the new gymnasium.
• Toddlers and EC1 will move to temporary modular classrooms on campus.
• EC2 will move to temporary classrooms in the Alfred House and a modular classroom behind the Alfred House.
• Kindergarten, first and second grades will remain where they are in Building B
• Fourth, fifth, and sixth grades remain where they are in Building C.

Summer 2018

• Modified Summer Institute Programs will take place.
• Summer Transition Program for EC-Kindergarten (TBD)

2018-2019 School Year
• Toddlers and EC1 will remain in modular classrooms on campus.
• EC2 will remain in the Alfred House and a modular classroom behind the Alfred House.
• Kindergarten, first and second grades will remain where they are in Building B.
• Third grade will remain in their new location in the building on LaCienega.
• Fourth, fifth, and sixth grades remain where they are in Building C.

Summer 2019
• Modified Summer Institute and Summer Transition Programs (TBD)

2019-2020 School Year
• All buildings will be completed; work will continue on the new play field.
• Toddlers, EC1, EC2, kindergarten, first, and second grade students will move to the new building on Clinton.
• Third grade will remain in the new building on LaCienega.
• Fourth, fifth, and six grades will remain in Building C.

January 2020: CAMPUS ENHANCEMENT SCHEDULED TO BE COMPLETE

Please note that the planned work schedule can be impacted by many factors (e.g. weather, unforeseen technical and cost issues, etc.) This schedule is our best estimate and is subject to change.